Winters Olympic ChallengeThursday 5th July 2012

Winters had 24 men working 24/7 for 5 weeks to complete a major power upgrade in BT Tower.

Winters were awarded a high profile and high pressure contract, to be completed in very tight timescales with considerable working restrictions imposed.
The project which essentially involved provision of power supplies, to serve new equipment racks for the Olympic Games, and was worth in excess £500,000. Winters received high praise from BT management for our performance and quality;

”If I may add my personal thanks to the Winters team for achieving this key milestone, on what has been a very challenging programme, ahead of schedule. I have been impressed by the quality of the works and professionalism I have observed from Winters as the project has progressed.”
Regards,
BT Operate
Power Policy Manager,